Capital Improvement Project Status
Minisink Valley Central School District voters approved a $36.9 million capital improvement project by a vote of 559-171 on Feb. 7, 2017.
The information provided below is the Capital Project Status presentation, given at the March 26, 2026 Board of Education meeting:
How a Capital Project Works
Design of a project
Work with Board of Education, Administration and Community
Review with the architects
Finalize and create a potential timeline and budget
Work with bond counsel
Estimate of how much of the work would be aidable
Determine best time to move forward with financing
Work with attorney
Develop the proposition
Develop the State Environmental Quality Review Act (SEQRA)
Set a vote timeline to hold the vote
Our vote was held Feb.7, 2017
2017 Capital Project Proposition
Shall the Minisink Valley Central School District be authorized to construct additions and improvements to and reconstruct various School District buildings and facilities and to construct a new sewage treatment plant, site improvements and incidental improvements and expenses at a maximum estimated cost of $36,935,000, to expend $5,000,000 from the Capital Reserve Fund therefore, and $31,935,000 or so much therefore as may be necessary shall be raised by the levy of a tax upon the taxable property of said School District and collected in annual installments; and in anticipation of such tax, obligations of said School District shall be issued?
Important Facts
The proposition authorizes the borrowing of money to finance the capital work
The district has 10 years to complete all of the work
The district’s proposition also authorized the use of the Capital Reserve Fund
Use of the Capital Reserve ($5 million) was designed for offsetting parts of the project that were not state aidable
The Capital Reserve has been expended in the required time (10 years)
Target Areas for the 2017 Capital Project
Construction of a new sewer treatment plant to replace the existing plant, which was approaching the end of its useful life. The new plant would have dual capacity to allow for regular maintenance to the system and avoid disruption to school operations on the main campus.
Infrastructure, maintenance and system-replacement needs in all school buildings, as identified by a state-mandated building condition survey conducted in the 2015-16 school year.
The construction of a new high school cafeteria to better accommodate student and building needs, and the repurposing of the existing, outdated cafeteria/kitchen to create new instructional space for programs that reflect 21st Century college and career pathways.
New York State Education Department (NYSED) Approval Process
How it works:
District develops architectural design and scope of work with its licensed architects.
Project must be submitted to NYSED’s Facilities Planning Division for the following reviews:
Architectural review
Engineering review
Financial review
Upon NYSED approval, a building permit is issued to the school district.
The district can then go out to bid for construction contracts.
New York State Education Department (NYSED) Final Submission Process
How it works:
District completes construction and submits the Certificate of Substantial Completion to NYSED
NYSED issues Certificate of Occupancy
District is required to submit final cost reports to NYSED for financial review.
Once completed, State Aid will begin to flow.
Elementary and Intermediate Schools: Covered Work
Replacement of VAT in A & D wings of the buildings
Replacement of the exterior original slate tile with new energy efficient insulated panels
Booster pump replacement
Replacement of retaining wall and steps in the back of the building
Repaving of parking areas, play surfaces and walkways
Refinishing of stage and gym floors
JV & Varsity softball dugouts replaced
Replacement of A Gym bleachers
Replacement of various electrical panels along with emergency lighting upgrades
Otisville Elementary: Covered Work
HVAC work in the main office
Various controls for HVAC with masonry work
Gym lighting
Middle School: Covered Work
Modernization of elevator
Booster pump replacement
VCT floor replacements
Replacement of two boilers
Gym lighting upgrade
Replacement of two door hardware units for ADA compliance
Unit ventilator replacements throughout the building
JV baseball dugouts replaced
Sidewalk and ramp replaced
High School: Covered Work
Pool dehumidification system replacement
Pool lighting
Replacement of locker rooms floors
Replacement of locker room bathrooms
Electronic control replacements across the building
Mechanical upgrades, including Uni-ventilator replacements
Replacement of electrical panels across the entire building
Drainage work around the high school
Sidewalk and wall replacement
Paving work at high school
Exterior lighting replacement
Reconstruction of the track
Reconstruction of the track bleacher wall
Drainage work at the soccer/lacrosse field
Drainage work around the track
Maintenance Facility: Covered Work
Paving of the entire facility
Potential of a bathroom (Removed)
Bus Garage: Covered Work
New water tank
Piping replacement
Heat exchanger
Wastewater Treatment Facility (WWTF) & Conversion of Old Facility: Covered Work
New treatment facility that is approximately 40% larger
Will allow for a partial shutdown during summer for maintenance
Will not require the district to build a new facility in the future
Convert the existing facility into a new support facility for the Buildings & Grounds Department
All B&G equipment will now be under a roof
High School Cardio & Weight Room: Scope of work
Cardio Room
Demolish existing storage room
Construct new facility
Purchase 23 pieces of equipment
Addition of televisions for instruction
Air condition the facility
Weight Room
Replace existing flooring
Add air conditioning
New paint on walls and ceilings
Purchase all new weight equipment
High School Electrical Work and Storage Room: Scope of Work
Electrical Work
Replace original switchgear
Replace existing transformer
Replace the electrical line from the pole to the transformer
Additional work of replacing original electrical boxes & main feed line
Now required to bury most of the line coming into the district
Storage Room
Create a large open storage room
Must have similar square footage
ES/IS Lunch Rooms Roof & HS Generator: Scope of Work
Full replacement of the roof over the entire ES/IS cafeteria
Replacement of the high school’s two generators with one large generator
Current generators have failed
High School Cafeteria Decision
The proposed cafeteria expansion was originally considered to address capacity needs and to improve the student dining experience
The project was planned prior to COVID-19
The district was in the design phase of the new cafeteria just prior to COVID-19
Everything changed after COVID-19
Post COVID-19 cost increases
Materials, equipment and labor cost have risen significantly beyond original estimates
Supply chain disruptions
Difficulty obtaining essential material like HVAC systems, Technology components and construction supplies
Labor challenges
Shortage at the time in skilled trades affected construction timelines
Updated project estimates
Estimates showed the cafeteria expansion would cost substantially more than initially budgeted
Enrollment trends
Population in the high school was down approximately 170 students
Population in the district was down approximately 350 students
Up-to-Date Capital Project Costs | |
Otisville Elementary: | $ 649,713.76 |
ES/IS: | $ 4,802,181.84 |
Middle School: | $ 4,487,857.69 |
High School: | $ 11,021,313.24 |
Maintenance Facility | $ 466,693.38 |
Bus Garage: | $ 159,135.01 |
Wastewater Treatment Plant: | $ 6,249,657.06 |
Former WWTP: | $ 68,113.80 |
Subtotal: | $ 27,904,665.78 |
Remaining Capital Project Work | |
High School electrical work: | $ 1,172,374.79 |
ES/IS roof & HS generator: | $2,046,991.72 |
Former WWTP: | $959,886.20 |
Subtotal: | $ 4,179,252.20 |
Previous subtotal: | $27,904,665.78 |
Total committed: | $ 32,083,918.49 |
Authorization: | $ 36,935,000.00 |
NOT borrowing at this time: | $4,851,081.51 |
For more information
Patrick Witherow
Assistant Superintendent for Business
845-355-5122
pwitherow@minisink.com
